Landed Costs

Add landed costs to manufacturing orders

The MRP Landed Costs module extends the Landed Costs feature to apply to Manufacturing Orders. This module allows adding landed costs to manufacturing orders, allocating costs to finished products, and automatically adjusting inventory values.

Landed Costs
Manufacturing Orders
Cost Allocation
Inventory Valuation

When to Use

Key points

  • Special material transportation costs

  • Quality inspection costs

  • Manufacturing insurance costs

  • Other additional costs not in BoM


Important Terminology

FieldsTrường dữ liệuDescription
Landed CostsChi phí phát sinhAdditional costs incurred beyond standard manufacturing costs
TargetĐối tượngManufacturing Orders to add costs to
Additional CostsChi phí bổ sungCosts to be allocated
Valuation AdjustmentsĐiều chỉnh định giáInventory value adjustments
Split MethodPhương pháp phân bổHow to divide costs among products

Create Landed Cost for Manufacturing Order

Steps

  • 1. Go to Inventory → Operations → Landed Costs.

  • 2. Click Create.

  • 3. Enter Date (cost occurrence date).

  • 4. Select Target: Manufacturing Orders.

  • 5. Select Manufacturing Orders to add costs to.

  • 6. Select Journal (accounting journal) and Account (cost account).


Add Additional Costs

In the Additional Costs tab, add costs to be allocated.

Steps

  • 1. Click Add a line.

  • 2. Select Product (cost type, e.g., Transportation, Insurance).

  • 3. Enter Cost (amount).

  • 4. Select Split Method (allocation method).

  • 5. Can add multiple cost lines.


Allocation Methods

Split Methods

MethodDescriptionUse When
By QuantityDivide by product quantityHomogeneous products
By Current CostDivide by current valueProducts with different values
By WeightDivide by weightTransportation costs
EqualDivide equallyFew products, similar values

Calculate Allocation

Steps

  • 1. After adding costs, click Compute.

  • 2. System automatically retrieves finished products from MO.

  • 3. Calculates allocation based on selected method.

  • 4. Displays results in Valuation Adjustments tab.


View Allocation Results

In the Valuation Adjustments tab, view detailed allocation for each product.

Key points

  • Product: Product name

  • Quantity: Quantity

  • Former Cost: Old value

  • Additional Landed Cost: Allocated cost

  • New Cost: New value


Validate Landed Cost

Steps

  • 1. Check allocation in Valuation Adjustments tab.

  • 2. Click Validate.

  • 3. System automatically creates journal entry.

  • 4. Adjusts inventory value.

  • 5. Updates product cost.


Journal Entry

When validated, system creates entry: Debit Stock Valuation Account, Credit Landed Cost Account.


View Journal Entry

Steps

  • 1. After validation, click Journal Entries button.

  • 2. View detailed journal entry.


Check Inventory Value

Steps

  • 1. Go to Inventory → Reporting → Valuation.

  • 2. Find product with landed cost added.

  • 3. View adjusted value.


Check Product Cost

Steps

  • 1. Open product.

  • 2. In Inventory tab, view Cost (includes landed cost) and Valuation (inventory value).


Traceability

Steps

  • 1. Open product.

  • 2. Click Valuation smart button.

  • 3. View Stock Valuation Layers.

  • 4. Find layer with type = "Landed Cost".


When to Use Landed Cost

Key points

  • Should use: Costs incurred after MO completion, unpredictable costs not in BoM, costs to allocate across multiple MOs

  • Should not use: Fixed costs that can be added to BoM, costs already in work center cost, insignificant small costs


Appropriate Allocation Methods

Key points

  • By Quantity: Homogeneous products, costs not dependent on value

  • By Current Cost: Products with different values, costs proportional to value

  • By Weight: Transportation costs, products with different weights

  • Equal: Few products (2-3 types), similar values


Workflow

Steps

  • 1. Complete MO before creating landed cost.

  • 2. Collect cost invoices.

  • 3. Create landed cost and select MO.

  • 4. Add costs with appropriate allocation method.

  • 5. Compute to view allocation.

  • 6. Check allocation results.

  • 7. Validate to post.


Special Situations

Key points

  • Costs for multiple MOs: Create one landed cost, select multiple MOs, costs will be allocated to all MOs

  • Adjust after validation: Cannot edit validated landed cost, must create new landed cost with negative amount or create manual journal entry

  • Landed cost for by-products: Only applies to finished products, by-products without cost share will not receive landed cost